Project Management Phase 2- Scheduling example

  This is a sample of drafting the timeline based on work structure..Each sub task may have a plan like this so that any new change to be accomplished can be given full review of whether t do or not or in others will affect what and where?

Column1 Column2 Column3 Column4 Column5 Column6 Column7
    Timeline        
  Deliverables 1st week 2nd week 3th week 4th week 5th week
             
1 Upgrade 5days        
2 Legacy Data Collection   5days      
3 Refining legacy data   5days      
4 Migrate the data     3days    
5 Add the new structure     3days    
6 Add new rules to employees     5days    
7 Apply grades     5days    
8 Test for salary element       7 days  
9 Check the reports related         4 days

























- The dependent task can be grouped after completion of main task to reduce the days utilized.
-Any change in requirement or adding new scope may force to break down of this plan which may show effect on cost or time span of the project,



No comments:

Post a Comment

Thanks for your comments submitted.,will review and Post soon! by admin.

COALESCE-SQL

Coalesce- return the null values from the expression. It works similar to a case statement where if expression 1 is false then goes to expr...